Beccs Big Build extension update 06/10/2024, together with latest pictures here.
Progress of works since last update:
- Ground floor roof (terrace floor) has been installed, making the ground floor watertight.
- Temporary roof in bar extension area installed, making the ground floor area below watertight for use.
- All remaining brickwork for ground floor and the terrace area has been completed including terrace coping stones.
- Note: the boarding on the south side of the terrace is temporary and is installed for safety purposes and to enable the scaffolding to be removed from site.
- All shower gullies have been installed in both new shower areas.
- Screeding of the ground floor has been completed.
- Initial painting of walls and ceilings has been completed.
- 1st fix of plumbing has been completed.
Next Steps:
- Install ducting for air intake / extraction in the ground floor
- 1st fix electrical installation
- Complete decoration of the walls.
- Shower room walls installation.
- Prepare outside area - steps, ramps for exits, ground areas and reinstate the car park to enable compound hoarding removal
- Note: carpentry, vinyl floor finishing and certain other internal installation activities need to wait until the screed floor has dried out.
Fundraising engagement and help from the entire club
We urgently need help and support from everyone in the club to assist with fundraising efforts for the Beccs Big Build. Every contribution, no matter how small, will make a difference and help us achieve our goal.
We strongly encourage those who haven’t already to get involved and support our fundraising initiatives by:
(a) Buy-a-Brick for the clubhouse, cost at £100, £200 or £300 (you are able to pay in monthly instalments). Details link here. Beccs are also looking at
(b) Look at other ways you can get involved including utilising any corporate / business contacts for sponsorship and matched funding opportunities, details link here.
(c) Easyfundraising on your internet shopping at NO cost to you, details link here.