The new changing room build is now back up to ground level. Despite having to battle with the weather, which included pumping out flooded 1m deep footings, Oxman have now installed the foul drains and laid the block and beam floor. The next stage is the damp proof course and then the outer walls will be seen to rise.
Thank you to everyone that has contributed in some way towards the Chairman's £50k fund. In particular your donations to the Buy a Brick campaign. But, there is still a way to so so... . if you haven't already committed yourself then now would be a good time to do so. Please email Tony Hinton on: tonynhinton1@gmail.com